[closed] Time Spent counts children's Time Spent hours
Cesar Sasaki (511●2●89●129)
| asked Sep 07 '11, 10:31 a.m.
closed Dec 14 '16, 2:20 a.m. by Ralph Schoon (63.3k●3●36●46)
Hi
Is there a way that the field "Time Spent" in a parent work item automatically update with the "Time Spent" field of his childrens?. For example : Parent Work Item Time Spent : 10h (automatically updates from the child work items) Child Work Item 1 Time Spent : 2h Child Work Item 2 Time Spent : 8h |
The question has been closed for the following reason: "The question is answered, right answer was accepted" by rschoon Dec 14 '16, 2:20 a.m.
Accepted answer
Ralph Schoon (63.3k●3●36●46)
| answered Dec 14 '16, 2:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
There is no built in capability (except the planning related features). You can create custom solutions. See https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ for an example.
Ralph Schoon selected this answer as the correct answer
|
One other answer
I am looking for the same functionality, but would also like this roll up information for estimated attribute as well.
|
Comments
I am looking for the same functionality, for both estimate and time spent.