Hi

Is there a way that the field "Time Spent" in a parent work item automatically update with the "Time Spent" field of his childrens?.

For example :

Parent Work Item

Time Spent : 10h (automatically updates from the child work items)


Child Work Item 1
Time Spent : 2h

Child Work Item 2
Time Spent : 8h

1 vote

Comments

I am looking for the same functionality, for both estimate and time spent.


The question has been closed for the following reason: "The question is answered, right answer was accepted" by rschoon Dec 14 '16, 2:20 a.m.

Accepted answer

Permanent link
There is no built in capability (except the planning related features). You can create custom solutions. See https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ for an example.
Ralph Schoon selected this answer as the correct answer

0 votes

Comments

Thank you so much Ralph!


One other answer

Permanent link
I am looking for the same functionality, but would also like this roll up information for estimated attribute as well.

0 votes

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 07 '11, 10:31 a.m.

Question was seen: 5,040 times

Last updated: Dec 14 '16, 10:34 a.m.

Confirmation Cancel Confirm