Hello.
I need to move many workitems to another project area. We had 2 projects in 1 project area organized in 2 teams and 2 timelines before and now we decided to separate them completely to 2 project areas.
How to do that?
Thanks
Martin

0 votes



2 answers

Permanent link
I assume this is another project area within the same repository.
There used to be a script you could run for RTC-2.0.0.2, but it doesn't
appear to still be working (work item 163729 is still Unresolved).
I've created a new request for this functionality, work item 170224.
Please feel free to add a comment to indicate your interest/support.

Cheers,
Geoff

On 6/28/2011 7:38 AM, mkobylan wrote:
Hello.
I need to move many workitems to another project area. We had 2
projects in 1 project area organized in 2 teams and 2 timelines
before and now we decided to separate them completely to 2 project
areas.
How to do that?
Thanks
Martin

0 votes


Permanent link
We are still running (for next few days) on RTC 2. However I don't know how to install this plugin into STS. I tried to replace the existing jar in plugins directory but it still works as the old jar.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jun 28 '11, 7:35 a.m.

Question was seen: 4,934 times

Last updated: Jun 28 '11, 7:35 a.m.

Confirmation Cancel Confirm