how do you track time between iterations


Patrick Doonan (111) | asked Jun 04 '08, 10:59 a.m.
When a task was worked on but not finished in an iteration. How do you move the task to the next iteration, while maintaining the time spend in the current iteration?


EX

Iteration 4
create my widget 4h 2h spent on task

Iteration 5
Since the task "create my widget" did not finish it needs to move to this iteration, with 2h ours left on the task. But I dont want to loose the time keeping from the previous iteration.

How is this accompished?

3 answers



permanent link
Dirk Baeumer (4811) | answered Jun 04 '08, 12:01 p.m.
JAZZ DEVELOPER
I would duplicate the work item and assigned the new one to 5 with the
remaining estimate and would close the one in I4

Dirk Baeumer
Agile Planning Component


pdoonan wrote:
When a task was worked on but not finished in an iteration. How do
you move the task to the next iteration, while maintaining the time
spend in the current iteration?


EX

Iteration 4
create my widget 4h 2h spent on task

Iteration 5
Since the task "create my widget" did not finish it
needs to move to this iteration, with 2h ours left on the task. But
I dont want to loose the time keeping from the previous iteration.

How is this accompished?

permanent link
Maren Nelson (611611) | answered Aug 11 '08, 9:47 p.m.
I have also experienced this issue regularly. Duplicating the work item is certainly an alternative, but painfully tedious.

Any chance we could get a "Split" option that could be smarter about field population in the new carry-over work item? (e.g. calculate and carry over the remaining time to be spent into the new work item's estimate field, retain any relationships/subscribers, etc.)

permanent link
Christof Marti (681) | answered Aug 12 '08, 2:26 a.m.
I've opened enhancement 59771 to track this, please feel free to open enhancement requests yourself whenever you encounter a missing feature.

Christof
Jazz Work Item team


marenn wrote:
I have also experienced this issue regularly. Duplicating the work
item is certainly an alternative, but painfully tedious.

Any chance we could get a "Split" option that could be
smarter about field population in the new carry-over work item? (e.g.
calculate and carry over the remaining time to be spent into the new
work item's estimate field, retain any relationships/subscribers,
etc.)