Active Project Areas > Timelines & current iteration/
Hi,
I am trying to work out how to change the current iteration/sprint. The trail sandbox I am using is set up with the RTC default scrum template.
In Active Project Areas > Timelines I see the following:
....|-> Main
........|-> Release 1.0
............|-> Sprint 1 (1.0)
............|--- Sprint 2 (1.0)
............|--- Sprint 3 (1.0)
............|--- Sprint 4 (1.0)
The current plan is 'Sprint 1 (1.0) '.
Note, the date format is .
Since it is 14/4/11 today, why isn't the current plan 'Sprint 2 (1.0) '?
Is it a manual process to change it? How do I mark one iteration/sprint as finished and another as started so that when I go to Plans > Current Plans I see the plan that matches the dates? I'd expect this to be automatic - but suspect I'm missing something here.
Thanks,
Trudi.
I am trying to work out how to change the current iteration/sprint. The trail sandbox I am using is set up with the RTC default scrum template.
In Active Project Areas > Timelines I see the following:
....|-> Main
........|-> Release 1.0
............|-> Sprint 1 (1.0)
............|--- Sprint 2 (1.0)
............|--- Sprint 3 (1.0)
............|--- Sprint 4 (1.0)
The current plan is 'Sprint 1 (1.0) '.
Since it is 14/4/11 today, why isn't the current plan 'Sprint 2 (1.0) '?
Is it a manual process to change it? How do I mark one iteration/sprint as finished and another as started so that when I go to Plans > Current Plans I see the plan that matches the dates? I'd expect this to be automatic - but suspect I'm missing something here.
Thanks,
Trudi.
4 answers
In Eclipse, load the project area into the project area editor, right
click on the iteration that you want to make current, and select the
"Set as Current" operation.
Also, there is work item 88813 requesting that the current iteration be
automatically set based on the current date. If you agree this behavior
should be supported, please add a comment to that work item indicating
your interest/support.
Cheers,
Geoff
On 4/13/2011 11:53 PM, trudiersvaer wrote:
click on the iteration that you want to make current, and select the
"Set as Current" operation.
Also, there is work item 88813 requesting that the current iteration be
automatically set based on the current date. If you agree this behavior
should be supported, please add a comment to that work item indicating
your interest/support.
Cheers,
Geoff
On 4/13/2011 11:53 PM, trudiersvaer wrote:
Hi,
I am trying to work out how to change the current iteration/sprint.
The trail sandbox I am using is set up with the RTC default scrum
template.
In Active Project Areas> Timelines I see the following:
...|-> Main
.......|-> Release 1.0
...........|-> Sprint 1 (1.0)
...........|--- Sprint 2 (1.0)
...........|--- Sprint 3 (1.0)
...........|--- Sprint 4 (1.0)
The current plan is 'Sprint 1 (1.0) '.
Note, the date format is
.
Since it is 14/4/11 today, why isn't the current plan 'Sprint 2 (1.0)
'?
Is it a manual process to change it? How do I mark one
iteration/sprint as finished and another as started so that when I go
to Plans> Current Plans I see the plan that matches the dates?
I'd expect this to be automatic - but suspect I'm missing something
here.
Thanks,
Trudi.