I've created a project from the Formal Project Management Process template and I've created some workitems.
On release plan (on WorkBreakDown and Schedule view) I can see the gantt chart and I can see workitems with different colors.
What is the difference between red and blue workitems?

Thanks in advance.
Bye

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Jan 04 '11, 12:38 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The "red" items are on the "critical path" ... i.e. you'd have to remove
or reschedule some of those items to decrease the amount of time
required to complete the iteration.

Cheers,
Geoff

On 1/4/2011 9:23 AM, angelo_corna wrote:
I've created a project from the Formal Project Management Process
template and I've created some workitems.
On release plan (on WorkBreakDown and Schedule view) I can see the
gantt chart and I can see workitems with different colors.
What is the difference between red and blue workitems?

Thanks in advance.
Bye

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.