I've created a project from the Formal Project Management Process template and I've created some workitems.
On release plan (on WorkBreakDown and Schedule view) I can see the gantt chart and I can see workitems with different colors. What is the difference between red and blue workitems? Thanks in advance. Bye |
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Jan 04 '11, 12:38 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The "red" items are on the "critical path" ... i.e. you'd have to remove
or reschedule some of those items to decrease the amount of time required to complete the iteration. Cheers, Geoff On 1/4/2011 9:23 AM, angelo_corna wrote: I've created a project from the Formal Project Management Process |