WOrk Items
Hi All,
Please help as this is very much needed for me. I am using RTC 2.0.0.2 I have few work items which i want to continue my work to the next iteration. I tried to right click and select Continue Work In option, but i dont find the same .
Please Help me ... Is there any other option for it?
Please help as this is very much needed for me. I am using RTC 2.0.0.2 I have few work items which i want to continue my work to the next iteration. I tried to right click and select Continue Work In option, but i dont find the same .
Please Help me ... Is there any other option for it?
One answer
The "continue" operation is only provided in the RTC Eclipse client from
the plan editor. In the Web, you need to just do the steps manually,
i.e. create a new work item, schedule it for the appropriate next
iteration (or backlog), create a "related" link between them, and adjust
the "estimate" for the new work item to reflect the work that already
has been done.
Cheers,
Geoff
On 12/8/2010 6:53 AM, preetskuul wrote:
the plan editor. In the Web, you need to just do the steps manually,
i.e. create a new work item, schedule it for the appropriate next
iteration (or backlog), create a "related" link between them, and adjust
the "estimate" for the new work item to reflect the work that already
has been done.
Cheers,
Geoff
On 12/8/2010 6:53 AM, preetskuul wrote:
Hi All,
Please help as this is very much needed for me. I am using
RTC 2.0.0.2 I have few work items which i want to continue my work
to the next iteration. I tried to right click and select Continue
Work In option, but i dont find the same .
Please Help me ... Is there any other option for it?