Removing Plans from 'Current Plans View'
We'd like to be able to remove plans which are associated with releases we have shipped. Is this possible?
|
4 answers
To extend on Eleni's question, one example is we have timelines created for releases we have delivered, however the last iteration is marked as the current iteration for that timeline and I don't see a way to un-make it the current iteration.
In the current plans view we show all of the plans for the last iteration of already delivered releases. Is there a way to mark these timelines as complete? |
Geoffrey Clemm (30.1k●3●30●35)
| answered Oct 13 '10, 12:14 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I agree one needs to be able to do this, but I don't see any way to do
it in the current Eclipse UI ... so I've submitted work item 136462 for it. Please feel free to subscribe or comment, to indicate your interest/support. Cheers, Geoff On 10/13/2010 9:38 AM, rtimothy wrote: To extend on Eleni's question, one example is we have timelines |
Geoffrey Clemm (30.1k●3●30●35)
| answered Oct 13 '10, 12:18 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can "delete" the plans, but I assume what you really want is to have
them no longer appear as "current", right? If so, see response to rtimothy below. Cheers, Geoff On 10/12/2010 9:22 PM, eleni wrote: We'd like to be able to remove plans which are associated with |
Correct, I'd rather not delete the old plans, just have them out of the way. I see there is an archive option for a release, not exactly sure what that does, but something similar might be nice for plans/timelines.
Don't get rid of the data, but don't clutter up my current work/views with old stuff. --tim |