Progress report in plan view does not show all children
I have a user story in Plan A with Team A working in iteration 1 of timeline 1.
The story has three children, two of which are in Plan A assigned to members of Team A. The third is in Plan B with Team B working in iteration 2 of timeline 2. Timeline 1 and 2 are running in parallel.
The details view of the story has a progress bar that shows the correct calculation of 10/16 hours complete. However, the plan view only shows the 6/8 hours complete of the two tasks that exist in iteration 1. Is this as designed, and if so, is there a way to create a view that shows a list of stories and the progress bar that is displayed in the details view?
Thanks.
The story has three children, two of which are in Plan A assigned to members of Team A. The third is in Plan B with Team B working in iteration 2 of timeline 2. Timeline 1 and 2 are running in parallel.
The details view of the story has a progress bar that shows the correct calculation of 10/16 hours complete. However, the plan view only shows the 6/8 hours complete of the two tasks that exist in iteration 1. Is this as designed, and if so, is there a way to create a view that shows a list of stories and the progress bar that is displayed in the details view?
Thanks.