Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Progress bar

Hi, I have a question about progress bar.

Regarding progress bar, I can find 2 different explanations as quoted below.

(1) http://jazz.net/projects/rational-team-concert/features/apt
>So if the past work time is 9 hours and you completed work you had estimated at 3 hours, the projection assumes that you'll need three times as much work time as estimated for the work that remains. Comparing the projected value to the remaining work time lets you know whether you are ahead or behind your target. The same projection is done for product backlogs using story points as the sizing attribute.


(2) http://jazz.net/library/presentation/19
RSDC2008_SDP24_DirkBaeumer.pdf :
>Resolved work: 9 hours / Total work: 11 hours
>Spent work time: 17 / Total work time: 96
>9 - 11/96 * 17 == 2 hours ahead

-----

My question is, which logic is correct ?

For example, if the situation is:

- Resolved work: 2 hours / Total work: 8 hours
- Spent work time: 8 / Total work time: 16

in case (1):
- remains: 6 hours
- the projection assumes: 6 * 16/8 = 12 h
- emaining work time: 8h

8 - 12 == 4 hours behind

in case (2)

2 - 8/16 * 8 == 2 hours behind

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jun 29 '10, 6:51 a.m.

Question was seen: 3,082 times

Last updated: Jun 29 '10, 6:51 a.m.

Confirmation Cancel Confirm