ClearCase hidden baseline dependencies - does RTC avoid this

I see discussion earlier on delivering work items with change-set
dependencies and options for dealing with it. ClearCase/UCM suffers from
an issue of potentially hitting hidden baseline dependencies when
delivering one or more activities while others may be in progress even
though there may be no change-set dependencies. This has been a real
sore point with some of our ClearCase users. I'm hoping this problem
doesn't exist in RTC. Can someone please confirm.

Thanks, Brian

0 votes



One answer

Permanent link
That is correct ... in Jazz, any dependencies are real (i.e. a
change-set only depends on the states of the files that it has changed).

Cheers,
Geoff (ClearCase Connector team)

Brian Gillan wrote:
I see discussion earlier on delivering work items with change-set
dependencies and options for dealing with it. ClearCase/UCM suffers from
an issue of potentially hitting hidden baseline dependencies when
delivering one or more activities while others may be in progress even
though there may be no change-set dependencies. This has been a real
sore point with some of our ClearCase users. I'm hoping this problem
doesn't exist in RTC. Can someone please confirm.

Thanks, Brian

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 03 '08, 11:38 a.m.

Question was seen: 4,801 times

Last updated: Mar 03 '08, 11:38 a.m.

Confirmation Cancel Confirm