We have hit a problem where a user can not deliver a change set, they receive the following error.

Assigned work item doesn't meet requirements
Problem
The associated work item must specify that the work is planned for the current iteration.

Reason
All change sets should be associated with a work item which is planned for the current iteration.

This makes it easier for the team to track its progress through the iteration and allows other users to understand why your changes were made.

Solutions
Open Associated Work Item(s)
Mark work item as planned for the current iteration


However the CS is linked to a work item whos Planned For field is set to the current iteration. The sequence of events that has triggered this is as follows.

Task planned for Iteration 1
Change Set created
Current Iteration changes to Iteration 2
Task planned for set to Iteration 2 (Not sure if was a manual or automatic update)
Change Set delivery attempted.

If you need docs please let me know ASAP, as we will have to force this CS through soon.

Regards,
Ian Hodges.

One answer



permanent link
Anthony Kesterton (7.5k7180136) | answered Apr 21 '10, 3:52 p.m.
JAZZ DEVELOPER
Hi,

We have hit a problem where a user can not deliver a change set, they receive the following error.

Assigned work item doesn't meet requirements
Problem
The associated work item must specify that the work is planned for the current iteration.

Reason
All change sets should be associated with a work item which is planned for the current iteration.

This makes it easier for the team to track its progress through the iteration and allows other users to understand why your changes were made.

Solutions
Open Associated Work Item(s)
Mark work item as planned for the current iteration


However the CS is linked to a work item whos Planned For field is set to the current iteration. The sequence of events that has triggered this is as follows.

Task planned for Iteration 1
Change Set created
Current Iteration changes to Iteration 2
Task planned for set to Iteration 2 (Not sure if was a manual or automatic update)
Change Set delivery attempted.

If you need docs please let me know ASAP, as we will have to force this CS through soon.

Regards,
Ian Hodges.


Hi Ian

Some ideas that may unblock this. Try going to the work item, change it back to iteration 1 and then back to 2 and make sure you save the work item. Check the work item really appears in the plan.

You may also want to try and disassociate and then re-associate the work item to that change set.

These actions may change you plans briefly, and add extra history to the change, but this may be acceptable if it fixes the problem.

I would also log a defect here on jazz.net so we can debug the problem.