Work Item template not setting Estimate field
I have set up a work item template in a 2.0.0.2 project that has several Tasks with an Estimate set. When we create a new set of tasks with "Create from Template", the tasks created don't have the Estimate value included.
Is this a bug or a setup problem? Any idea how I get that value included?
Thanks for the help,
Julie Rotter
Is this a bug or a setup problem? Any idea how I get that value included?
Thanks for the help,
Julie Rotter
6 answers
On Tue, 09 Mar 2010 17:53:00 +0100, jmrotter
<jmrotter> wrote:
Hello Julie,
attributes of type 'Duration' are not supported in work item templates in
RTC2.0.0.2. Values of unsupported attributes are simply ignored and not
included when capturing/instantiating a template. RTC3.0 will be the first
release that supports the complete set of work item attributes.
Regards,
Jan.
--
Jan Wloka
Jazz Work Item Team
<jmrotter> wrote:
I have set up a work item template in a 2.0.0.2 project that has
several Tasks with an Estimate set. When we create a new set of
tasks with "Create from Template", the tasks created don't
have the Estimate value included.
Is this a bug or a setup problem? Any idea how I get that value
included?
Thanks for the help,
Julie Rotter
Hello Julie,
attributes of type 'Duration' are not supported in work item templates in
RTC2.0.0.2. Values of unsupported attributes are simply ignored and not
included when capturing/instantiating a template. RTC3.0 will be the first
release that supports the complete set of work item attributes.
Regards,
Jan.
--
Jan Wloka
Jazz Work Item Team
On Mon, 12 Apr 2010 17:53:01 +0200, jmrotter
<jmrotter> wrote:
Full template support for all work item attributes, including approvals,
will be available in 3.0.
Regards,
Jan.
--
Jan Wloka
Jazz Planning & Tracking Team
<jmrotter> wrote:
Jan, Is there a way to include Approvals in the template? In trying
to create a template from a task with Approvals, the Approvals
weren't created in tasks created from the template.
I take it this isn't available either? Is it being considered for 3.0
as well?
Thanks!
Full template support for all work item attributes, including approvals,
will be available in 3.0.
Regards,
Jan.
--
Jan Wloka
Jazz Planning & Tracking Team
Hello Julie,
attachments are included in workitem templates in RTC 3.0.
Regards,
Jan.
--
Jan Wloka
Jazz Planning & Tracking Team
On Mon, 10 May 2010 22:52:58 +0200, jmrotter
<jmrotter> wrote:
attachments are included in workitem templates in RTC 3.0.
Regards,
Jan.
--
Jan Wloka
Jazz Planning & Tracking Team
On Mon, 10 May 2010 22:52:58 +0200, jmrotter
<jmrotter> wrote:
One more follow-up question related here: Will 3.0 include
attachments in templates? So, if a story has a file attachment, for
instance, that would be included in the template.
Thanks once again!
Julie