I have set up a work item template in a 2.0.0.2 project that has several Tasks with an Estimate set. When we create a new set of tasks with "Create from Template", the tasks created don't have the Estimate value included.

Is this a bug or a setup problem? Any idea how I get that value included?

Thanks for the help,
Julie Rotter

6 answers



permanent link
Jan Wloka (4161) | answered Mar 16 '10, 4:29 a.m.
JAZZ DEVELOPER
On Tue, 09 Mar 2010 17:53:00 +0100, jmrotter
<jmrotter> wrote:

I have set up a work item template in a 2.0.0.2 project that has
several Tasks with an Estimate set. When we create a new set of
tasks with "Create from Template", the tasks created don't
have the Estimate value included.

Is this a bug or a setup problem? Any idea how I get that value
included?

Thanks for the help,
Julie Rotter


Hello Julie,

attributes of type 'Duration' are not supported in work item templates in
RTC2.0.0.2. Values of unsupported attributes are simply ignored and not
included when capturing/instantiating a template. RTC3.0 will be the first
release that supports the complete set of work item attributes.

Regards,
Jan.

--
Jan Wloka
Jazz Work Item Team

permanent link
Julie Rotter (3866) | answered Mar 16 '10, 12:59 p.m.
Thanks for the information!

permanent link
Julie Rotter (3866) | answered Apr 12 '10, 11:51 a.m.
Jan, Is there a way to include Approvals in the template? In trying to create a template from a task with Approvals, the Approvals weren't created in tasks created from the template.

I take it this isn't available either? Is it being considered for 3.0 as well?

Thanks!

permanent link
Jan Wloka (4161) | answered Apr 13 '10, 4:29 a.m.
JAZZ DEVELOPER
On Mon, 12 Apr 2010 17:53:01 +0200, jmrotter
<jmrotter> wrote:

Jan, Is there a way to include Approvals in the template? In trying
to create a template from a task with Approvals, the Approvals
weren't created in tasks created from the template.

I take it this isn't available either? Is it being considered for 3.0
as well?

Thanks!


Full template support for all work item attributes, including approvals,
will be available in 3.0.

Regards,
Jan.

--
Jan Wloka
Jazz Planning & Tracking Team

permanent link
Julie Rotter (3866) | answered May 10 '10, 4:43 p.m.
One more follow-up question related here: Will 3.0 include attachments in templates? So, if a story has a file attachment, for instance, that would be included in the template.

Thanks once again!
Julie

permanent link
Jan Wloka (4161) | answered May 11 '10, 4:31 a.m.
JAZZ DEVELOPER
Hello Julie,

attachments are included in workitem templates in RTC 3.0.

Regards,
Jan.

--
Jan Wloka
Jazz Planning & Tracking Team


On Mon, 10 May 2010 22:52:58 +0200, jmrotter
<jmrotter> wrote:

One more follow-up question related here: Will 3.0 include
attachments in templates? So, if a story has a file attachment, for
instance, that would be included in the template.

Thanks once again!
Julie

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.