I want to copy a ProjectAreaA in a new ProjectAreaB.

I used RQMCopyUtil and I can see that all artifacts are migrated.

But I've done a lot of change in Role and Permission so I want to be able to migrate also this information.

So what I can do?

Any contribution is appreciated

Ciao Oreste

0 votes



One answer

Permanent link
If you use the Admin (RTC) client you are able to create a "Process Template" based on "ProjectAreaA". This template will pick the changes you have done for Roles, Permissions, WorkItem customization, workflows etc.

In the RTC client, right click on your project area (ProjectAreaA) and select "Create Process Template" and give it a name.

When you create a new project area (ProjectAreaB) simply use the process template you have created

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 01 '10, 10:43 a.m.

Question was seen: 6,963 times

Last updated: Mar 01 '10, 10:43 a.m.

Confirmation Cancel Confirm