Hi Team,


We have a usecase wherein we need the estimation effort in minutes, but by default the efforts is displayed in hours. 

Is it configured anywhere ? can we change the default hours display to minutes ?

Thanks

0 votes



One answer

Permanent link

By default, you can select hours, minutes, seconds in the estimate in the web UI. You use the drop down to select what you want. In the project area administration there is the section Planning>General where you can choose to only support hours.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,498
× 1,328
× 1,221

Question asked: Oct 08 '24, 3:56 a.m.

Question was seen: 314 times

Last updated: Oct 08 '24, 11:08 a.m.

Confirmation Cancel Confirm