Command to copy/clone a workitem
![]() Hi All,
Our development team using the API commands to automate RTC/EWM workitem creation and other operations. We are using Work Item Command Line Version 6.0.1 and could not find a command to clone/copy a workitem in a project area. Currently we are working on RTC 6.0.6.1 and planning to upgrade to EWM 7.0.2 in April. Please let me know the respective command and if needed any additional information.
Thanks,
Vinay
|
Accepted answer
![]()
Ralph Schoon (62.3k●3●36●43)
| answered Feb 27, 7:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Mar 01, 6:08 a.m. As far as I remember, I have not implemented such a command. The tool is reasonably well documented and there is not such a command.
Ralph Schoon selected this answer as the correct answer
Comments Another idea might be to export a work item into a CSV file, modify the CSV file is needed and then import the CSV file into the other project area. This could be an alternative approach. |