We are using DNG & ETM 702. Configuration Management not enabled in DNG & Baselines enabled in ETM. GC is not used.

Following DNG traceability matrix shows Text Execution status for Test Plan version 1.
DNG Traceability Matrix
Version 1 of Requirements is Tested.
Test Plan version 2 is being prepared. How to clear the Test Execution Status from DNG Traceability View.

0 votes



One answer

Permanent link

Hi Chid,


Since this is a incoming link to DNG, I believe you will have to do that from ETM side itself

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,033

Question asked: Apr 11 '22, 4:10 a.m.

Question was seen: 1,057 times

Last updated: Apr 11 '22, 5:26 a.m.

Confirmation Cancel Confirm