It's all about the answers!

Ask a question

Iterations are not visible for selection when generating the execution records for the test cases


Jyothi P (111) | asked Sep 02 '20, 8:46 a.m.

Created iteration from dashboard. Created a new test plan and pulled in test suite into the plan. Selected that test suite. Clicked on generation execution records. Here the iteration section is unassigned even though the iterations have been created.  


Can you provide the steps for populating the iterations in the execution records?

One answer



permanent link
Krupa Gunhalkar (4512) | answered Sep 25 '20, 7:03 a.m.
JAZZ DEVELOPER

 Hi Jyothi,


Create Project timeline and iterations at the Project area level using Project Admin permissions.
Attach this project timeline to the test plan under Test Schedule section. Save the test plan.
Now any TCERs created under the test plan will reflect the iterations created under the Project Timeline.

Hope this helps,
Krupa Gunhalkar

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.