How to change Execution Mode of a Test Suite that has been started?


Steven Melcher (6012831) | asked Mar 15 '18, 11:34 a.m.

 Using Jazz 6.0.3 iFix10, is it possible to change the Execution Mode of a Test Suite that is already started from Sequential to Parallel?


The Test Suite was designed to be run in parallel, but was accidentally started in sequential.

One answer



permanent link
Subhajit Bhuiya (6222) | answered Apr 03 '18, 3:14 a.m.
JAZZ DEVELOPER

Once it is started in one mode, you can not change it for the run. But you can always do it for next run. You can also go to test case section of test suite and mark the test suite to run in parallel mode. Then it will by default run in parallel mode.