How to transfer a TCER into a TSER? [RQM 6.0.4]

 We have a situation where a TCER was generated by running a test case from the test case artifact.  


I have a TSER that I would like to have these results in but I don't see to be able to find any way to transfer a separate TCER artifact into a TSER, nor the ability to transfer the TCR artifact into another TCER.  Also roll-up can only be done intra-TCER correct?  

0 votes

Comments

 Anybody?



One answer

Permanent link

Hi, Tom

Your understanding is correct, No, No and Yes to your questions.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Mar 06 '18, 5:25 p.m.

Question was seen: 1,611 times

Last updated: Mar 08 '18, 7:09 p.m.

Confirmation Cancel Confirm