Mark Ingebretson (58515036) | asked Sep 28 '09, 11:08 a.m.
In an Iteration Plan, on the Planned Items tab, if there are
warnings/errors (like an item is past its due date), a warning is
displayed across the top bar of the Plan window. I can click on the
warning and get the details. However, if I fix the problem (or it has
been fixed by another user), the warning doesn't go away, even when I
"refresh" the plan. (At this point, when I click on the warning, the
detail box is empty.) I have to close the plan entirely and reopen it
in order to make the warning go away.

One answer



permanent link
Johannes Rieken (1.2k1) | answered Sep 29 '09, 3:53 a.m.
Mark Ingebretson wrote:
In an Iteration Plan, on the Planned Items tab, if there are
warnings/errors (like an item is past its due date), a warning is
displayed across the top bar of the Plan window. I can click on the
warning and get the details. However, if I fix the problem (or it has
been fixed by another user), the warning doesn't go away, even when I
"refresh" the plan. (At this point, when I click on the warning, the
detail box is empty.) I have to close the plan entirely and reopen it
in order to make the warning go away.

I've created
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/95517
to track this issue.

--
Cheers, Johannes
Agile Planning Team