 Hello Everyone,

 My scenario is that I have created Work item type example Task-1 ,I want to share Task-1 work item type into another project area with work flow,using process sharing ,WI type did not shared.
Is there any way to share WI type into more than one project area?

Regards
Amruta

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Nov 28 '17, 4:50 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

You can define that the process for one project area (the child project area) should be inherited from another project area (the parent project area), but you cannot selectively share just a single work item type.   Also, note that if you modify a work item type in the child project area, the child project area will no longer inherit work item type changes from the parent project area.

Rohini Kumar selected this answer as the correct answer

Comments
Ralph Schoon commented Nov 28 '17, 5:09 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.