Could someone confirm it is true or not that in RTC 2.0, changes to process template will be applied automatically to existing project area which created using it ?
We know this was not true in 1.0.1.1 as we had to add the change to the process configuration source directly. |
2 answers
Thanks, Ryan, for confirming that.
Changes to a template are not applied to existing projects. |
Changes to a template are not applied to existing projects.
Behavior here is the same in RTC 1.x and 2.x. --- Ryan Manwiller Jazz Team |