It's all about the answers!

Ask a question

How to create other dependency/link type


Sutthi Bualek (414) | asked Dec 17 '07, 4:12 a.m.
I'm working with Osellus Asia Pacific co.,ltd. and our product, IRIS Process Author, supports dependency type for each work items like "Start-Start", "Start-Finish", "Finish-Finish" while link type of Links field of Jazz supports only
- Related
- Duplicated
- Blocks
- Depends On
- Parent
- Child

Is it possible to add more our link/dependency types in Process Specification?
If not, is there the ways to custom my new field type?

Moreover, is it possible to create predefined link between each work items in Process Specification?

Thanks,
Sutthi

3 answers



permanent link
Sutthi Bualek (414) | answered Dec 18 '07, 3:26 a.m.
Sorry Jazz team!

Actually I'd like to create link/dependency type named "Predecessor" and "Successor", not "Start-Start", "Start-Finish", "Finish-Finish".

Could you please tell me how to create new link types?



I'm working with Osellus Asia Pacific co.,ltd. and our product, IRIS Process Author, supports dependency type for each work items like "Start-Start", "Start-Finish", "Finish-Finish" while link type of Links field of Jazz supports only
- Related
- Duplicated
- Blocks
- Depends On
- Parent
- Child

Is it possible to add more our link/dependency types in Process Specification?
If not, is there the ways to custom my new field type?

Moreover, is it possible to create predefined link between each work items in Process Specification?

Thanks,
Sutthi

permanent link
Andre Weinand (4811) | answered Dec 18 '07, 8:38 a.m.
The Work Items editor will automatically show newly introduced link
types where the source or target is a Work Item. However, I don't think
it is already possible to introduce link types dynamically (e.g. in the
process specification). If this is still true, you'll need to add a
link type definition to your plugin.xml file.

--andre


On 2007-12-18 09:28:03 +0100, sutthi@osellus-dot-com.no-spam.invalid
(sutthi) said:

Sorry Jazz team!

Actually I'd like to create link/dependency type named
"Predecessor" and "Successor", not
"Start-Start", "Start-Finish",
"Finish-Finish".

Could you please tell me how to create new link types?



I'm working with Osellus Asia Pacific co.,ltd. and our product,
IRIS Process Author, supports dependency type
for each work items like "Start-Start",
"Start-Finish", "Finish-Finish" while link type
of Links field of Jazz supports only
- Related
- Duplicated
- Blocks
- Depends On
- Parent
- Child

Is it possible to add more our link/dependency types in Process
Specification?
If not, is there the ways to custom my new field type?

Moreover, is it possible to create predefined link between each work
items in Process Specification?

Thanks,
Sutthi

permanent link
Sutthi Bualek (414) | answered Dec 18 '07, 9:11 p.m.
Hi Weinand!

How could I reach/prepare my plugin.xml?
Or do you mean plugin of Eclipse?

Please give me a suggestion or a document.

Thanks,
Sutthi

The Work Items editor will automatically show newly introduced link
types where the source or target is a Work Item. However, I don't think
it is already possible to introduce link types dynamically (e.g. in the
process specification). If this is still true, you'll need to add a
link type definition to your plugin.xml file.

--andre


On 2007-12-18 09:28:03 +0100, sutthi@osellus-dot-com.no-spam.invalid
(sutthi) said:

Sorry Jazz team!

Actually I'd like to create link/dependency type named
"Predecessor" and "Successor", not
"Start-Start", "Start-Finish",
"Finish-Finish".

Could you please tell me how to create new link types?



I'm working with Osellus Asia Pacific co.,ltd. and our product,
IRIS Process Author, supports dependency type
for each work items like "Start-Start",
"Start-Finish", "Finish-Finish" while link type
of Links field of Jazz supports only
- Related
- Duplicated
- Blocks
- Depends On
- Parent
- Child

Is it possible to add more our link/dependency types in Process
Specification?
If not, is there the ways to custom my new field type?

Moreover, is it possible to create predefined link between each work
items in Process Specification?

Thanks,
Sutthi

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.