How can I create a plan for specific Work items

I need to create a plan for specific Work items. We have defined a Work item type called Theme.
I want to be able to have a plan for those items not based on Sprints. What is the best way to create such a plan?

0 votes



One answer

Permanent link
RTC Plans are basically work item queries and they are basically always based on an owner and an iteration. There are no plans without iterations.

You can use expressions to filter away things such as other types. You can simply use work item queries for only the types you want to see. That is pretty much what you can do as far as I can tell. See https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals#Planning and the product help to understand the basic concepts.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Oct 31 '16, 2:53 p.m.

Question was seen: 1,509 times

Last updated: Nov 01 '16, 2:52 a.m.

Confirmation Cancel Confirm