Brett Bohnn (94111153) | asked Sep 27 '16, 5:16 p.m.
 Hi,

Are there plans to provide changes set for local configuration management in RQM? And without change sets to deliver, is "merge configuration" the way to merge (deliver) changes from streams, baselines? 

Thanks,
Brett

Comments
Don Yang commented Sep 28 '16, 2:40 a.m.

I 2nd to this question and want to know if we have plan to support change set.
The plan work item:
https://jazz.net/jazz02/web/projects/Rational%20Quality%20Manager#action=com.ibm.team.workitem.viewWorkItem&id=136904
does not have any progress for a long time.

One answer



permanent link
Paul Slauenwhite (8.4k12) | answered Nov 16 '16, 12:57 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
Change sets are not yet supported and are not in plan.  See RQM plan item [QM] Support Change Sets (136904) for more details. 

Merge configuration will allow changes from a baseline/stream to be merged into another stream.  One could imagine using a 'change set' stream that would be used for editing test artifacts, which could be merged with the 'mainline' stream when all the changes are complete.