Preserving task hierarchy when importing plan from MS Project into RTC
When importing project plan from Microsoft Project into RTC version 6.0.2, will the tasks hierarchy be preserved? What are the steps to ensure that the tasks hierarchy is preserved?
What format should the plan be in before data importing? |
One answer
I have tested the project plan import and was successful in preserving the tasks hierarchy. Project plan need to be exported in xml format first before the import.
|
Your answer