Preserving task hierarchy when importing plan from MS Project into RTC

When importing project plan from Microsoft Project into RTC version 6.0.2, will the tasks hierarchy be preserved? What are the steps to ensure that the tasks hierarchy is preserved?
What format should the plan be in before data importing?

0 votes



One answer

Permanent link
I have tested the project plan import and was successful in preserving the tasks hierarchy. Project plan need to be exported in xml format first before the import.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,120

Question asked: Sep 21 '16, 1:34 p.m.

Question was seen: 4,218 times

Last updated: Oct 27 '16, 2:54 p.m.

Confirmation Cancel Confirm