Work Item - Can you color those WI's in a plan that are due

Can you color those WI's in a plan that are due in the next 48hrs?

0 votes



2 answers

Permanent link
no, this is not currently possible. we only support coloring overdue work items - you can achieve that using the expression "verification:afterDueDate"
please file an enhancement request.

--
MikeS
Jazz Agile Planning team

pawrampe wrote:
> Can you color those WI's in a plan that are due in the next 48hrs?

2 votes

Comments

Hello. Any improvement in RTC 4.0 about this request?

Thanks in advance,

 Chemi.


Permanent link
no, this is not currently possible. we only support coloring overdue work items - you can achieve that using the expression "verification:afterDueDate"
please file an enhancement request.

--
MikeS
Jazz Agile Planning team


Mike,

I would like to colorize overdue work item. I used the expression "verification:afterDueDate" in RTC V3.0.1.2. But it did not work.
Could you tell me how to set up to colorize overdue work item in RTC V3.0.1.2 ?

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 24

Question asked: Aug 13 '09, 11:28 a.m.

Question was seen: 6,078 times

Last updated: Aug 22 '14, 7:34 p.m.

Confirmation Cancel Confirm