Is there a way to change link between Test Case and Test Case Result?


Christelle COIC (11211) | asked May 19 '16, 11:32 a.m.
 Our version : 4.0.2

Context : 2 test plans with quite same test cases in it : one tester made executions on a test plan but it was the wrong one.

Question : how can we do to report the results created from the executions made from plan2, into the plan1 ?

Thanks for your help!!
Regards.
Christelle Coïc

Comments
Brett Bohnn commented May 19 '16, 3:27 p.m.

Hi Christelle,

There could be a more creative approach but you cannot change the test plan associated to a completed test case execution record, result. There is a new feature in 6.0.2 that might allow that but I have not looked into yet.

Thanks,
Brett

One answer



permanent link
Don Yang (7.2k2194127) | answered May 19 '16, 9:58 p.m.
Hi Christelle,

In v4.0.2, it is definitely no way to change test plan in the execution result.
Even in latest version of RQM, you may be able to modify the test environment(see below new features)
https://jazz.net/downloads/rational-quality-manager/releases/6.0.1?p=news#TOC_B
but still changing test plan in the test result is not possible.

Thanks