Is there a way to re-sequence test scripts in an RQM test plan?  For example, if I add a new test script, it gets the next available number (for example, 10), however it does not fall in the correct order of the test scripts. ( I want it inserted between scripts 3 and 4).  Thank you.

2 answers



permanent link
Brett Bohnn (94111157) | answered Feb 24 '16, 5:08 p.m.
He Charlene,

You can move test cases up or down in a test plan, as shown here below. Is that what you are trying to do?



Comments
Charlene Joyce commented Feb 25 '16, 8:24 a.m.

Hi Brett.

Thank you for replying.  I am actually trying to re-sequence the test scripts within a test case. 


permanent link
Charlene Joyce (1111) | answered Feb 26 '16, 10:00 a.m.
Checked with IBM support.  Cannot change the test script ID since it is a primary key in the DB.  There is also currently no way to move test scripts around (similar to steps within a script).