A change set can be associated to one or several work-items.

In the history view of a file, for example, when a change set is associated to several work-items, the change set icon is slightly different and an hover of the mouse over the icon displays an info about the change set that includes the list of work-items.

But the history view also displays the summary of one work-item in the Comment column.

When there are multiple work-items associated to a change sets, which work-item is selected to provide the content of the comment column ?

Thanks,

Nicolas

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Aug 16 '15, 12:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I believe it is the work item that has been most recently associated with the change set.