Hello, I have some question about "Execution Trend report".
1)How to use this report? What use-case is supposed to?
To show "Execution Trend report", it is needed that user put actual end date for test schedule(Test milestone).
It means that before test schedule finish user can't see any trend report, doesn't it?
2)How can I check such execution trend during a test schedule is in progress?
>It means that before test schedule finish user can't see any trend report, doesn't it? (1)
If so, how can I check such execution trend during a test schedule is in progress?
I assume only planned start&end date informations are needed and are enough for this purpose, no need to set actual end date.
3)How to check "Execution Trend report" by Test Milestone.
Even if I set Test Milestone for each TER and set "Test Milestone" parameter for "Execution Trend report",
the TER count(planned/actual) seems to show all TER associated with Test Plan (not each Test Milestone).
How can I see "Execution Trend report" by each Test Milestone?
Any ideas?
I use RQM 1.0.1.1 (Japanese)
1)How to use this report? What use-case is supposed to?
To show "Execution Trend report", it is needed that user put actual end date for test schedule(Test milestone).
It means that before test schedule finish user can't see any trend report, doesn't it?
2)How can I check such execution trend during a test schedule is in progress?
>It means that before test schedule finish user can't see any trend report, doesn't it? (1)
If so, how can I check such execution trend during a test schedule is in progress?
I assume only planned start&end date informations are needed and are enough for this purpose, no need to set actual end date.
3)How to check "Execution Trend report" by Test Milestone.
Even if I set Test Milestone for each TER and set "Test Milestone" parameter for "Execution Trend report",
the TER count(planned/actual) seems to show all TER associated with Test Plan (not each Test Milestone).
How can I see "Execution Trend report" by each Test Milestone?
Any ideas?
I use RQM 1.0.1.1 (Japanese)
One answer
Note: This post is 5+ years old.
Please upgrade to the latest version of RQM (see https://jazz.net/downloads/rational-quality-manager/) and review the product documentation (see https://jazz.net/help-dev/clm/topic/com.ibm.help.common.jazz.calm.doc/com.ibm.help.common.jazz.calm.doc_eclipse-gentopic1.html) and jazz.net resources (see https://jazz.net/help). If your issue persists, please ask a new question (https://jazz.net/forum/questions/ask), open a defect (see https://jazz.net/mystuff/#tab=workitems), or open a PMR (see http://www-01.ibm.com/support/docview.wss?uid=swg21507639).
Please upgrade to the latest version of RQM (see https://jazz.net/downloads/rational-quality-manager/) and review the product documentation (see https://jazz.net/help-dev/clm/topic/com.ibm.help.common.jazz.calm.doc/com.ibm.help.common.jazz.calm.doc_eclipse-gentopic1.html) and jazz.net resources (see https://jazz.net/help). If your issue persists, please ask a new question (https://jazz.net/forum/questions/ask), open a defect (see https://jazz.net/mystuff/#tab=workitems), or open a PMR (see http://www-01.ibm.com/support/docview.wss?uid=swg21507639).