I want to maintain different baseline for a module in Requirements Managements. If I generate report for that module, I am getting the report for the current baseline only. Is there any way to get the report for the older baseline??

Please help me...

1

0 votes


Accepted answer

Permanent link
Hi Praveen,

You can refer https://jazz.net/wiki/bin/view/Main/RRCReportServiceFAQ#How_can_I_generate_a_report_from for information on how to obtain the  ID of the baseline (snapshot).
To filter by snapshot, you can use https://server:port/rm/publish/[artifact_format]?snapshotId=id

Regards,
Prasad
Praveen Kumar selected this answer as the correct answer

1 vote

Comments

Thanks Subramanya Prasad, It helps me

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 84

Question asked: Feb 25 '15, 11:59 p.m.

Question was seen: 4,798 times

Last updated: Mar 04 '15, 8:06 a.m.

Confirmation Cancel Confirm