I want to maintain different baseline for a module in Requirements Managements. If I generate report for that module, I am getting the report for the current baseline only. Is there any way to get the report for the older baseline??

Please help me...

Accepted answer


permanent link
Subramanya Prasad Pilar (4.6k16) | answered Feb 26 '15, 11:29 a.m.
edited Feb 27 '15, 6:20 a.m.
Hi Praveen,

You can refer https://jazz.net/wiki/bin/view/Main/RRCReportServiceFAQ#How_can_I_generate_a_report_from for information on how to obtain the  ID of the baseline (snapshot).
To filter by snapshot, you can use https://server:port/rm/publish/[artifact_format]?snapshotId=id

Regards,
Prasad
Praveen Kumar selected this answer as the correct answer

Comments
Praveen Kumar commented Mar 04 '15, 8:06 a.m.

Thanks Subramanya Prasad, It helps me