How do you have sprints automatically set to current sprint when date is reached?
Hi All,
I have Rational Team Concert 4.0.6. The Timeline/iteration is not activating the next sprint when the date is reached
Example:
In my main development - (I have these sprints) Sprint A (12/31/15 - 1/20/15) Sprint B (1/21/15 - 2/10/15) Sprint C (2/11/15 - 3/10/15) How can I auto activate the current Sprint C when the date is "2/11/15"? |
Accepted answer
Kevin Ramer (4.5k●9●186●201)
| answered Feb 06 '15, 4:33 p.m.
edited Feb 06 '15, 5:30 p.m. by Geoffrey Clemm (30.1k●3●30●35)
This has not yet been implemented. It is requested in: [JAF][Process] Automatically update the "current" iteration based on the current date. (88813) .
If you have a developerWorks ID, add a Vote to this : https://www.ibm.com/developerworks/rfe/execute?use_case=viewRfe&CR_ID=35133 Daniel Ruebush selected this answer as the correct answer
Comments Is this available in 5.0.2 or still under voting ?
Geoffrey Clemm
commented Mar 18 '16, 11:26 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
It is not yet implemented or in a plan, so still under voting.
|