Progress Bar for Epics and Story Work Items Removed?
One answer
Comments
Same here.
So I inspected my project areas and I noticed that in the presentation editors,
com.ibm.team.apt.editor.story and .epic. The Progress UI element is there, but it is not attached to any attribute. I reattached it to the 'work progress' attribute. And now it shows up when I view stories or epics.
However, I noticed that this is now default behavior. Anytime I create a projectArea the editor presentations don't have the 'work progress' attribute linked to the Progress UI element. This worked prior to our upgrade to 5.0.2. So, for all new project area created I have to make this update after it is created.
Any ideas on where to look? A way to dump the built-in process templates and inspect them for errors?
You likely use a process template to create the project area. This might be broken. If you fix it in a project are and create a new template from that for further use, you should be done.
You can also test on a test server, if you can delete the current built in templates and redeploy them.
It is also a good practice, to create your own process template (from a built-in template) with its own ID and use that, instead of the built in templates.
Comments
Yaron Norani
Dec 27 '15, 1:07 p.m.Hi, I get same issue. Process is based on SCRUM and include local customization.