Swathi Brahma (1145) | asked Jun 26 '14, 2:24 p.m.
I was trying to add multiple time estimates to a single work item type (for ex: Dev Estimates, Test Estimates, Automation Estimates etc.). Even though I created separate attributes (with different attribute IDs) of the type “duration” and added it to the work item type, updating one estimate, updated all the other estimates as well.

I see the same issue when I try  to add multiple approvals and multiple attachment attributes to a work item type.

Comments
sam detweiler commented Jun 26 '14, 4:52 p.m.

hm. this sounds more like the same variable was put onto the presentation 3 times.
I have never seen the behavior u mention.

One answer



permanent link
Swathi Brahma (1145) | answered Jun 26 '14, 4:55 p.m.
Hi Sam,

I just got to know that this was a defect (https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=239658) that has been fixed in RTC version 5 as part of another work item (https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=307060)

So I will try to upgrade our server to CLM v5 and see if that will fix the problem.