Is it possible to create a new workspace from a stream as the stream existed on a specific date and time? Lets assume there were no snapshots at that point.

It would then be nice that all existing updates changeset would be listed to bring the workspace to the current stream, but not necessarily that important requirement.

Thanks.

0 votes



One answer

Permanent link
You can do this by hand, by creating a workspace that flows with that
stream, and then in each component, open the history of that component
and drop all change sets after that date.

Dropping the change sets is easy in the GUI (just multi-select from the
most recent change set to the first one after the selected date), but it
would be a bit tedious if you have lots of components.

I've created work item 78895 to make this easier by allowing the date to
be specified at workspace creation time.

Cheers,
Geoff



rineholt wrote:
Is it possible to create a new workspace from a stream as the stream
existed on a specific date and time? Lets assume there were no
snapshots at that point.

It would then be nice that all existing updates changeset would be
listed to bring the workspace to the current stream, but not
necessarily that important requirement.

Thanks.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 18 '09, 9:23 a.m.

Question was seen: 6,793 times

Last updated: Apr 18 '09, 9:23 a.m.

Confirmation Cancel Confirm