Is there a way to add multiple Parent link in a work item?
Hi,
We have a scenario, where a single task is required to have multiple parent work items because the same code has to be deployed by multiple teams.
Is there a way to add multiple parent work item for a single task?
We are using RTC v5.0
|
Accepted answer
Hi Shuchita,
There is no currently such function but we have an enhancement for that: https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=114389. You can subscribe to this work item to track the progress there. Let us know if that helps. Shuchita Tripathi selected this answer as the correct answer
|