Migration from TM to RQM - iterations
I allowed RQM to import all assets from TM including any old iterations that were defined.
where did it store that data ? I'm not getting an error on one of my reports that is indicating that (Tester report using TER Count) - which shows : Parameter loading failed: : PlanIterationTestcase is not a parameter group
the test plan and test case options on the edit box say but cannot display the values presumably due to this error (version is 1.0.1)
where did it store that data ? I'm not getting an error on one of my reports that is indicating that (Tester report using TER Count) - which shows : Parameter loading failed: : PlanIterationTestcase is not a parameter group
the test plan and test case options on the edit box say but cannot display the values presumably due to this error (version is 1.0.1)
8 answers
Yes, Iterations from TestManager are migrated as milestones for a testplan.
I think same apply for CQTM migration
You didn't really answer my query .. where exactly can I find them in RQM ? I only migrated two plans, and neither have a milestone that as you indicate was an iteration in TM ... so if they're not on the plan - where are they stored so I can associate or delete ?