Planing issues
Hi,
I am using RTC 4.0.6 v on RHEL 6.2. I have problems in scheduling the workitems in plans according to the orgenisational given plan dates. Problem is : I have a PLAN A, in which i have created 6 workitems grouped as per usecases. Usecase A has 3 WIs and Usecase B has another 3 WIs. Ideally Usecase B will only start after the completetion of Usecase A. When I give estimated time in UsecaseB's WI then the bars of Gantt chart has become red with no error notification and also after adding the predeceors and successors still the problem persist. Can you please guide me in scheduling the workitems of Plans as per the given project plan dates. I am not able to do so.... Thanks and Regars Shruti |
Be the first one to answer this question!
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Phat Plan type/scheduler do you use?
Hi Shruti,