Hi,
   I am working in CLM 4.0.5. I created a story and created two child task for that story with Task 1 estimated 7 hours and task 2 estimated 6 hours. The story progress bar shows the total time 13 hours for both task but when i resolved any task, the progress bar doesn't update. (Green bar doesn't appear). I have checked this on different browsers, IE 9, Firefox, 25, Chrome, etc.



And when i hover the mouse on progress bar, it shows 2 of 3 items completed although I have created only two child tasks for this story.


Is this a bug or some configuration issue?

Thanks & Regards,
Tariq Ashraf

One answer



permanent link
Don Yang (7.7k21108137) | answered Mar 29 '14, 8:36 p.m.
The reason you see 2 of 3 completed is because it counts story itself as one item. This does not sound reasonable, hence there is an enhancement workitem here:
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=193444

Some argue that that should be a defect Not a RFE. Even though 2 of 3 completed, should progress bar show 66.7% progress? this is not clear as of what should be expected result.Some discussions are here:
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&itemId=_NCm4sBpnEeOc-d8etB4oBA
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=215301&tab=com.ibm.team.workitem.tab.links

You may want to comment in above workitems to clarify what are expected results or contact support to get clarification.