Can not modify project area
Tony ONeill (1●1●2)
| asked Jan 24 '14, 3:38 p.m.
retagged Jan 30 '14, 5:26 p.m. by Dejan Custic (285●5) I am trying to modify a projects area to add an administrator to a project that I just created. It states that I do not have permission
|
One answer
Here is a reference and how to do this.
Open your process specification. Go to Project Configuration-->Permissions-->Process-->Modify a Project Area-->Modify the Process Specification
|
Your answer