Affected work items on Plan
In Plans, When work items are marked for delivery for a specific date and if dates are moved will it be possible to get the list of affected work items alone for the specific work item which has its dates rescheduled ? If so how can this be done.
Thanks,
Adhithya
|
Accepted answer
How are you specifying the delivery date for a work item.
One way to do so is by specifying the delivery date by setting the due date of the work item.
You can set the color option with the expression dueDate:<today.
This way you can get all the work items which have past the due date.
Ralph Schoon selected this answer as the correct answer
Comments Yes its based on the due date . Could you please let me know where can this be set ?
Some work items might not have the due date configured. You would have to add the presentation to the work item editor. If you ask about the colorization see https://jazz.net/help-dev/clm/topic/com.ibm.team.apt.doc/topics/t_create_pla_nmode_web.html
|