It's all about the answers!

Ask a question

Affected work items on Plan


Bharath Adhithya (5213352) | asked Nov 21 '13, 7:08 a.m.
In Plans, When work items are marked for delivery for a specific date and if dates are moved will it be possible to get the list of affected work items alone for the specific work item which has its dates rescheduled ? If so how can this be done.

Thanks,
Adhithya 

Accepted answer


permanent link
Aradhya K (1.4k54345) | answered Nov 21 '13, 9:44 a.m.
JAZZ DEVELOPER
How are you specifying the delivery date for a work item.
One way to do so is by specifying the delivery date by setting the due date of the work item.
You can set the color option with the expression dueDate:<today.
This way you can get all the work items which have past the due date.
Ralph Schoon selected this answer as the correct answer

Comments
Bharath Adhithya commented Dec 03 '13, 12:51 a.m. | edited Dec 03 '13, 12:51 a.m.

Yes its based on the due date . Could you please let me know where can this be set ?


Ralph Schoon commented Dec 03 '13, 1:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Some work items might not have the due date configured. You would have to add the presentation to the work item editor. If you ask about the colorization see https://jazz.net/help-dev/clm/topic/com.ibm.team.apt.doc/topics/t_create_pla_nmode_web.html