Hi All,

I am noticed something strange with rtc 4.0

*Open a formal project and create a phase plan

*Plan view > Workbreakdown & Schedule view

* Create work items as follows ( Parent Task with 3 child tasks) and add successor links. Then close tasks one after another. So you will see a plan something like this below.

However I see errors in the plan

X : Successor workitem was closed before predecessor workitem.

I am not sure why this error comes though the resolution dates of the workitems are in correct order only.

          Please let me know what is the reason for this error.

Thanks in advance!

0 votes

Comments


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 7,487
× 1,220

Question asked: Nov 20 '13, 7:26 a.m.

Question was seen: 5,333 times

Last updated: Jan 06 '14, 7:14 p.m.

Confirmation Cancel Confirm