Greetings,

I am having trouble updating the "Time Spent" field of a task in RAD Client. When I press Save, it reverts back to previous value.

I found a workaround in the webclient by updating the "Time Remaininig" value, then the "Time Spent" field will get updated in the RAD Client.

Is this a bug in the RAD Client side? Thanks!

2 answers



permanent link
Kelvin Ko (3632) | answered Feb 24 '09, 2:23 p.m.
Greetings,

I am having trouble updating the "Time Spent" field of a task in RAD Client. When I press Save, it reverts back to previous value.

I found a workaround in the webclient by updating the "Time Remaininig" value, then the "Time Spent" field will get updated in the RAD Client.

Is this a bug in the RAD Client side? Thanks!


After playing around with this some more, I found that if I make the change, then tab out of the "Time Spent" field before I click save on RAD Client, it saves the value most of the time.

If I just change the value and press <Enter> key without tabbing out of the "Time Spent" field, it reverts back to the old value most of the time.

permanent link
Johannes Rieken (1.2k1) | answered Feb 27 '09, 4:48 a.m.
kelf wrote:
kelfwrote:
Greetings,
I am having trouble updating the "Time Spent" field of a
task in RAD Client. When I press Save, it reverts back to previous
value.
I found a workaround in the webclient by updating the "Time
Remaininig" value, then the "Time Spent" field will
get updated in the RAD Client.
Is this a bug in the RAD Client side? Thanks!

After playing around with this some more, I found that if I make the
change, then tab out of the "Time Spent" field before I
click save on RAD Client, it saves the value most of the time.

If I just change the value and press <Enter> key without tabbing
out of the "Time Spent" field, it reverts back to the old
value most of the time.


This is a known issue and being tracked in
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/65523.
Feel free to subscribe.

--
Cheers, Johannes
Agile Planning Team

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.