Gannt Chart shows work item completion date, where is that attribute?
Accepted answer
Carson,
as far as I can tell, this is data that is calculated in the plan and not stored as attribute of the work item. You can, as far as I can tell not access them as attribute. There might be "virtual" attributes in the plan view editor that might allow to show this information as column.
There are several derived presentations that work this way. For example the progress you can see on some work items.