Can I check people actual work load among project areas ?


cun cun (655) | asked Feb 11 '09, 8:09 a.m.
Some people have been assigned to different project areas. They've defined different ratio of their efforts for the different team areas. But if I want to know someone's total work status, how is the person's total actual work loads and how about his/her total progress on different projects, is there a direct or workaround way to know that?
Thanks!

One answer



permanent link
Johannes Rieken (1.2k1) | answered Feb 12 '09, 3:58 a.m.
cun1000000 wrote:
Some people have been assigned to different project areas. They've
defined different ratio of their efforts for the different team
areas. But if I want to know someone's total work status, how is the
person's total actual work loads and how about his/her total progress
on different projects, is there a direct or workaround way to know
that?
Thanks!


Hey there. Currently the team load can be configured for a single team
area or (with 2.0M2d1) project area but not for multiple. As a work
around you can duplicate the team load section and in the team central
view and configure them accordingly.

--
Cheers, Johannes