Can I check people actual work load among project areas ?
Some people have been assigned to different project areas. They've defined different ratio of their efforts for the different team areas. But if I want to know someone's total work status, how is the person's total actual work loads and how about his/her total progress on different projects, is there a direct or workaround way to know that?
Thanks! |
One answer
cun1000000 wrote:
Some people have been assigned to different project areas. They've Hey there. Currently the team load can be configured for a single team area or (with 2.0M2d1) project area but not for multiple. As a work around you can duplicate the team load section and in the team central view and configure them accordingly. -- Cheers, Johannes Agile Planning Team |