Is it possible to change a work item type, for example, from a task to a story, or vice versa? If work items cannot be changed, what is the best workaround? Should we resolve the offending work item and create another work itrem of the proper type?

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Jan 28 '09, 11:09 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Yes, the type of a work item can be changed. Just click on the modify
button to the right of the type display, and select the new type.

Cheers,
Geoff

PatSilva wrote:
Is it possible to change a work item type, for example, from a task to
a story, or vice versa? If work items cannot be changed, what is the
best workaround? Should we resolve the offending work item and create
another work itrem of the proper type?