data transfer between RRC and RTC
Shimon Nir (24●11●16)
| asked Jun 12 '13, 7:11 a.m.
retagged Jun 12 '13, 10:35 a.m. by Michelle De Armas (261●2)
Hi
After building a custom field in RRC say "effort estimation" as an attribute to a requirement, I need to transfer its value to a corresponding RTC WI attribute. The reason being that in RTC the effort estimation is calculated just before the actual work starts, in the Requirement, (RRC) the effort estimation was done to support cost estimate and proposal to the customer. Thus there may be a gap between the tow estimates, because of miscalculation. It will be then very easy to show this on a dashboard and understand which requirement/WI causes the gap. Of course it can be done in RRDI but then to build such a report is somewhat cumbersome. Has anyone stumbled into this need ? Thanks Shimon |
One answer
You would need to customize the RTC attribute using a script based function so it inherits the value from RRC. Afterwards, you could create a custom report for your dashboard.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.