Why Backlog is in Current plan view?


Don Yang (7.7k21109138) | asked May 06 '13, 2:00 a.m.
I notice that when open Current Plan or My Current Plan view in RTC, backlog type plan is always included. My understanding is that current plan is for the plan having current iteration. But backlog iteration is not set as current iteration, why it will show in current plan view(or my current plan)?

Accepted answer


permanent link
Millard Ellingsworth (2.5k12431) | answered May 10 '13, 8:18 p.m.
FORUM ADMINISTRATOR / JAZZ DEVELOPER
I'm pretty sure it's because it is always available and always active. It is assigned to a special backlog iteration that doesn't have start and end dates and represents all pending work for the project, so it is always "current".
Don Yang selected this answer as the correct answer

Comments
Don Yang commented May 19 '13, 6:07 a.m.

Thanks Millard for the answer.