It's all about the answers!

Ask a question

Changing Process Templates


Sean Burke (3789144247) | asked May 03 '13, 6:30 p.m.
 If a group starts using the default process template in a project area but wants to change to scrum is this possible?  Would there be an ramifications?

One answer



permanent link
Clement Liu (1.5k54349) | answered May 03 '13, 7:46 p.m.
edited May 03 '13, 8:18 p.m.
Hi Sean,

Have you made any modification to your existing template? They will be lost when you switch to a new template. I'd suggest to create a new project area with the Scrum template and move the work items in your existing project area to the new one. 

Hope it helps. Thanks. 

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.